Ideal for use in plants requiring power of from 1 to 1.5 Mw's for use in areas that do not require emissions controls. The GPB15 offers electrical efficiency of 28% and an overall Cogeneration thermal efficiency of 78%. It is ideal for cogeneration use in: Offshore oil platforms, shopping malls, data centers, industrial process plant applications, hospitals, universities / colleges , prisons, high rise apartment / office buildings and hotels with district heating and cooling loads, pharmaceuticals, LNG Terminals, oil production - water flood projects, and other facilities with significant thermal and electrical loads. |
|
A Closer Look
Offers electrical efficiency of 28% and an overall Cogeneration efficiency of 79%
|
More GPB Series Gas Turbines
Download More Information |
| Power plant performance vs Temperature - US Customary Units (Switch To Metric) | |||||||
| Inlet air Temp. | Electric Output | Fuel Consumption | Exhaust Temp. | Exhaust Flow | HRSG Steam | CHP Efficiency | |
| F | kWe | kW | °F | lb /sec | lb/hr | % | |
| 59 | 1,444 | 6,072 | 997.5 | 17.6 | 11,220 | 77.6 | |
| 32 | 1,250 | 6,622 | 975 | 19 | 11,450 | 76 | |
| 86 | 1,620 | 5,570 | 960 | 21 | 11,000 | 78.8 | |
| 95 | 1,186 | 5,415 | 1,007 | 15.9 | 10,780 | 79.9 | |
| Units Weights and Dimensions - US Customary Units (Switch To Metric) | ||
| Dimension (L,W,H) | Weight | |
| inches | lbs | |
| 21 x 7 x 11 | 24,200 | |
Fuel:
Can be confured with dual fuel systems for both liquid and gas fuels
Note:
Performance based on 4 inch and 10 inch H2O intake/exhaust pressure losses
Sea level site
* Contact Kawasaki Application Engineering for site-specific performance
* Not for guarantee
|
Standard Equipment
|
Special Features
|